A large factory may have a large appetite for electricity but very little spare roof or land area. A data centre may face a similar challenge as its power needs rise. In both cases, the limits of the site can shape the options for clean energy. So, what is open access, and why might an off-site project matter to these businesses?
The answer starts with how companies procure power. Renewable generation doesn’t always need to sit beside the facility that uses the electricity. An eligible business may be able to contract for power from a separate plant and use the grid to receive it. That option brings its own rules, costs and operating checks.
Understanding these details helps a company judge whether off-site solar can fit its energy needs. This guide explains the model, who may qualify and what to assess before moving ahead. Power can come from elsewhere.
For businesses asking “what is open access“, Section 42 of the Electricity Act, 2003 provides the starting point. It gives eligible consumers access to the transmission or distribution network so they can buy power from a generator of their choice. Green Energy Open Access applies this route to renewable electricity.
The Green Energy Open Access Rules, 2022, cover solar, wind, hydro and energy storage systems charged using renewable sources. They also let entities procure green power through a developer, power market or distribution company.
The rules set a central framework for renewable energy procurement, while state electricity regulators define many of the charges and operating conditions. As a result, eligibility, costs and approval requirements can vary across states.
※ If you’re assessing how regulatory changes could affect your power procurement plans, learn more about the Electricity Amendment Act 2026 and its implications for C&I businesses.
A factory can sign a Power Purchase Agreement (PPA) with an off-site solar plant. The plant injects electricity into the grid. The transmission network carries power over longer distances, while the distribution network delivers it to the factory. The local distribution company still operates its network.
Meters record electricity injected and drawn, and energy accounting matches these quantities under approved schedules. This accounting doesn’t mean the factory receives a dedicated flow from that solar plant; the grid serves many users at once. Solar generation and factory demand may not match each hour.
Banking may credit eligible surplus energy for later use, subject to state rules and charges. Under the central rules, banked energy must be adjusted within the same banking cycle and can’t be carried forward to subsequent cycles. Banking is an accounting arrangement, not physical storage.
The eligibility rules help answer the question of “what is open access” for businesses. Non-captive consumers need contracted demand or sanctioned load of at least 100 kW. Contracted demand is the capacity agreed with the distribution company, while sanctioned load is the connection’s approved capacity.
Businesses can combine multiple connections to meet the 100 kW threshold, provided they’re within the same electricity division of a distribution licensee.
Captive consumers have no minimum load requirement under the Green Energy Open Access Rules. However, they must qualify under Rule 3 of the Electricity Rules, 2005, as amended in March 2026.
For a power plant to qualify as captive, users must hold at least 26% ownership and consume at least 51% of its total annual generation. The 2026 amendment also clarifies ownership through group companies, consumption limits in group captive projects and captive status verification. Grid and technical requirements still apply.
The PPA tariff isn’t the full supply cost. Landed cost includes the energy price and relevant network and regulatory charges. These costs form an important part of the question of “what is open access” for businesses assessing their procurement budgets.
Depending on the route and state regulations, charge heads may include:
Banking charges: Charges for adjusting surplus energy for later use.
Each charge has a different purpose. CSS relates to the cross-subsidy revenue a distribution company may lose when a consumer switches supply. Additional surcharge relates to fixed power purchase costs that may remain after a consumer shifts. Parallel operation charges may apply to captive plants running alongside the grid.
These charges don’t apply in the same way to every project. The Green Energy Open Access Rules set a central framework, while other provisions and state orders affect wider arrangements.
CEEW’s May 2026 report reviews six charges: CSS, additional surcharge, standby, banking, parallel operation and wheeling. It highlights differences in state rules. Compare local tariff orders and the site’s consumption profile; a low PPA tariff alone doesn’t prove savings.
Open access gives businesses access to renewable generation beyond their own sites, including facilities with limited room for on-site solar systems. This is one reason companies researching what is green energy open access may consider off-site solar.
A well-matched contract may lower procurement costs. Savings depend on the tariff, charges, consumption pattern and state rules, so compare the full cost with the current supply arrangement. A fixed tariff can support budgeting.
It can also increase the renewable share of a company’s electricity use and support its clean energy plans.
Review electricity use with energy, finance and operations teams before choosing a supply model.
The concerned nodal agency must approve a complete application within 15 days. If it doesn’t issue a decision within this period, the application is deemed approved, subject to technical requirements set by the appropriate Commission. However, approval alone doesn’t confirm that transmission capacity and other technical arrangements are ready for power supply.
Open access gives businesses a practical way to bring off-site renewable power into their energy mix. However, choosing the right arrangement requires more than comparing solar tariffs. Your electricity demand, consumption patterns, grid connectivity and applicable state charges all shape the project’s value.
With experience in solar project development and off-site solar solutions, Enerparc helps businesses explore suitable renewable energy options and plan their transition towards cleaner power. The right approach can support better energy planning while creating a lasting impact on your sustainability goals.
So, are you ready to explore solar open access for your business? Write to us here, schedule a consultation, or call (+91) 80-4941-4941 to discuss your energy requirements and find a suitable off-site solar solution.
Open access charges are the extra costs you pay to move electricity from a renewable power plant to your facility through the grid. Depending on your project and state rules, these may include transmission, wheeling, cross-subsidy surcharge, banking and standby charges. They affect your final power cost.
An Open Access Power Purchase Agreement is a contract between your business and a power generator. It sets out the amount of electricity, price per unit, contract period, delivery terms and each party’s duties. Your facility draws power through the grid, while meters track the agreed supply.
India’s Green Energy Open Access Rules let eligible consumers buy renewable electricity through the grid. The 2022 rules set a 100 kW demand or sanctioned-load threshold, exempt captive users from a minimum load, and cover approval, banking and charges. Later amendments clarify demand aggregation and application requirements.
Maharashtra follows the central Green Energy Open Access Rules, 2022, through MERC’s Distribution Open Access Regulations, 2016, as amended in 2023. Non-captive consumers need contracted demand or sanctioned load of at least 100 kW.
MSEDCL consumers can combine multiple connections within the same electricity circle to meet this threshold. Short-term applications go to MSLDC, while medium- and long-term applications go to the State Transmission Utility (STU).
Uttar Pradesh follows the central Green Energy Open Access Rules, 2022, alongside UPERC’s Open Access Regulations, 2019, as amended in 2024. A May 2026 order relaxed check and standby meter requirements for consumers connected at voltage levels up to 650 volts and revised fees for lead GEOA consumers.
UPERC also repealed its separate 2022 captive verification regulations, effective 1 April 2026, following changes to the central captive power rules.