Investing in on-site solar means making choices that can shape your facility’s energy use for years. You need a clear view of the technical setup, the grid connection and the way electricity will be accounted for.
For industrial solar projects, net metering affects how you account for the electricity your system generates and exports. Understanding the applicable arrangement early helps you assess its impact on energy costs, system sizing and project returns.
Net metering is a billing arrangement for a grid-connected solar system. It records the electricity your facility takes from the grid and the surplus it sends back.
Your commercial solar panel produces direct current (DC). An inverter changes it into alternating current (AC), which your facility can use. Solar power supplies your loads first. If generation exceeds demand, surplus electricity can flow to the grid, subject to approval. When solar output is lower than demand, you draw power from the grid.
A bidirectional meter records both flows. Your utility uses these readings to calculate the net energy balance for billing.
Under net metering, exported units are deducted from imported units. The resulting energy balance is billed or adjusted under your state’s rules. Any credit carried forward or surplus payment depends on the approved settlement method.
For example, say your facility imports 50,000 kWh and exports 12,000 kWh during a billing period. If your arrangement allows a one-to-one unit adjustment, your net energy import is 38,000 kWh. This shows the unit calculation only, not your final bill.
Your bill may also include fixed charges, demand charges, electricity duty and other items set by the relevant tariff order. These may not be adjusted through net energy credits. Review your DISCOM’s tariff structure to understand which charges remain payable even when solar exports reduce your net energy consumption.
| Arrangement | How your electricity is accounted for |
| Net metering | Exported units are deducted from imported units. |
| Net billing | Imported and exported electricity are valued at separate tariffs. |
| Gross metering | Commercial solar generation and electricity use are measured and settled separately. |
Under the Central Electricity (Rights of Consumers) framework, net billing values imported electricity at the retail tariff and exported electricity at a feed-in tariff set by the State Commission.
With gross metering, the utility purchases your solar generation at the applicable feed-in tariff. You pay the retail tariff for the electricity your facility consumes. State Commission rules decide which arrangements are available to each consumer category.
Before choosing a system size, check the rules for your state and electricity connection. Eligibility can depend on your consumer category, sanctioned load or contract demand, proposed solar capacity and local distribution transformer capacity.
Sanctioned load or contract demand is the approved power limit for your connection. Transformer capacity matters because the local network must be able to accept the electricity your industrial solar power system may export.
The Ministry of Power’s 2021 rules say metering arrangements must follow State Commission regulations. Where state rules don’t provide for net metering, net billing or net feed-in, the Commission may allow net metering for loads up to 500 kW or sanctioned load, whichever is lower. This is a conditional provision, not a national capacity limit.
CEEW’s April 2025 review examined 29 state and Union Territory regulations notified up to 31 December 2024. It found that 24 required solar rooftop systems above 1 kW, while 23 allowed capacity up to the sanctioned load. Transformer-level limits ranged from 15% to 100% across states. These variations can affect the permitted system capacity and layout of an industrial solar rooftop project.
The review also found that 21 regulations provided compensation for excess generation at the end of the settlement period. Check current rules for your project location.
Your operating hours affect how much solar power you can use directly. If your factory runs during sunny hours, it may consume more of its solar generation. If your site uses less electricity, then more power may flow to the grid.
This makes the match between solar generation and facility demand an important part of project planning. Export value depends on the settlement method and rate set under state rules. Some arrangements allow unused credits to carry forward or provide compensation at the end of a settlement period.
West Bengal’s 2025 rooftop solar regulations set a settlement period that generally runs from 1 April to 31 March. They provide for net metering, net billing and gross metering for eligible prosumers. Check the applicable settlement rules to understand how unused credits and exported units will be treated in your commercial solar power projects.
Review your electricity use by time of day, operating shifts and season. Compare expected solar output with demand, then assess likely exports against the settlement rate. This gives you a stronger basis for system sizing than roof area alone.
Before you apply, work through these checks with your project team:
The process varies by state and distribution company. West Bengal’s 2025 regulations set out application, technical review and connection requirements. Follow the latest procedure issued by your distribution licensee and obtain the required approvals before commissioning your system.
Net metering can play an important role in how you manage electricity costs and use surplus solar power. However, the value of this arrangement depends on your facility’s energy needs, operating hours and applicable state regulations. Well-planned industrial solar projects should account for all three before you commit to its design.
With its experience in commercial and industrial solar solutions, Enerparc can help you explore suitable solar options and assess your project’s requirements. Take the next step towards a cleaner energy future. Write to us here, schedule a consultation, or call (+91) 80-4941-4941 to discuss your solar project and explore the right solution for your business.
Yes, commercial and industrial consumers can use net metering in states where the rules allow it. Your eligibility depends on your consumer category, sanctioned load or contract demand, system capacity and local grid limits.
Check your State Commission’s latest rules and your DISCOM’s approval process before planning a commercial and industrial solar installation.
Yes. You can install solar for your own use without net metering. An off-grid or behind-the-meter system can supply your facility without exporting power to the grid. If you want a grid connection, check whether net billing, gross metering or another approved arrangement applies to your connection.
Neither option is always better. Net metering adjusts imported and exported electricity in units, while net billing values them at separate tariffs. Your better choice depends on your state’s rules, electricity use and export rate. Compare the likely value of surplus power before choosing your solar arrangement.
Your utility compares the electricity you import from the grid with the electricity your solar system exports. Under net metering, exported units are deducted from imported units. For example, 12,000 units exported against 50,000 imported leaves 38,000 net units if a one-to-one adjustment applies under your state’s rules.
Surplus electricity can be sent to the grid if your system has approval and the required meter. Your DISCOM then adjusts or values those exported units under the state’s rules. Depending on the arrangement, unused credits may carry forward or receive compensation at the end of the settlement period.